Authors:
John C. Reis (reis@pr.erau.edu)
August Ryan Wilhelmsen
James D. Stormer
Suggested Courses:
Thermodynamics & Heat Transfer
Level:
Junior & Senior
Based on "To Dissent or Not to Dissent"*
I. Narrative
Alison Turner is a department manager at a commercial nuclear
generating plant. She is also a member of the Plant Nuclear Safety
Review Committee (PNSRC). The committee's responsibilities include
reviewing and approving design changes, and submittals to the
Nuclear Regulatory Commission (NRC).
Today Alison finds herself in a difficult situation. PNSRC is
meeting to decide what to do about a heat exchanger problem.
Routine testing on the previous morning revealed degraded cooling
water flow and high differential pressure in both heat exchangers
in the safety system. The most likely cause of the problem is
sand accumulation in the filter at the cooling water inlet to
the heat exchangers. The two heat exchangers are in parallel,
and when operating at full heat transfer capacity, each one individually
provides sufficient cooling to safely operate the plant. Two
heat exchangers are used in case one of them fails.
After extensive analysis by engineers in the mechanical engineering
and nuclear safety and licensing departments, they have concluded
that the cooling water flow falls 30 percent below the minimum
requirement set by the technical specifications under which the
plant is licensed. To allow for continued plant operation at
the current cooling water flow rate, nuclear safety and licensing
has prepared a Justification for Continued Operation (JCO),
based on mechanical engineering's analysis, for submission to
NRC. PNSRC is now meeting to decide whether to approve the JCO
and forward it to NRC. If the JCO is not approved, the plant
must be shut down for expensive repairs.
Seven members of the PNSRC are present, enough for a quorum.
Alison is the least senior member present. From the outset of
the meeting, committee chair Rich Robinson has made it clear that
it is important to act quickly, since any shutdown will cost the
company, and ultimately the rate payers, a lot of money in additional
fuel costs. He says that "the JCO seems fine," and
calls for an open vote.
Alison has reviewed the JCO and is uncomfortable with an assumption
made in the analysis. The assumption made is that the degraded
flow through the cooling water side of the heat exchanger (~30%
less than nominal) has a negligible effect on the overall heat
transfer coefficient (U). Single failure criteria requires the
plant to assume the loss of one heat exchanger in accident situations.
Alison is concerned that if one heat exchanger fails, the combined
loss of heat transfer capacity and lower coolant flow rate would
result in a dangerous operating condition. The JCO does not discuss
what might happen under that contingency.
Alison is considering requesting a delay in the PNSRC vote so that a more complete analysis can be conducted. She is concerned, however, that Rich may oppose the delay from fear that a negative result may require the plant to be shut down to make repairs.
II. Numerical Problems
Given:
Volumetric Flow Rate - Hot Side = 2000 gpm
Volumetric Flow Rate - Cold Side - initial = 4000 gpm
Thi (Temperature - Hot Side - Inlet)= 300 F
Tci (Temperature - Cold Side - Inlet)= 85 F
Tho nominal (Temperature - Hot Side - Exit - Initial Case) = 125 F
Tho maximum (Temperature - Hot Side - Maximum Limit) = 140 F
hc initial (Heat Transfer Coefficient - Cold Side - Initial) = 634 BTU/ft2-hr-F
hh (Heat Transfer Coefficient - Hot Side) = 634 BTU/ft2-hr-F
A (Area for Heat Transfer) = 10,000 ft2
k (Thermal Conductivity)= 36 BTU/hr-ft-F
L (Tube Thickness) = 0.5"
cp (Specific Heat Capacity) = 1 BTU/lbm-F
EQUATIONS:
1) FIND THE NOMINAL HEAT TRANSFER RATE
Q = 1*106 lbm/hr * 1 BTU/lbm-F * ( 300 F -
125 F) = 1.75 * 108 BTU/hr
2) FIND THE NOMINAL Tco
3) DETERMINE Tlm
4) CALCULATE NOMINAL U
OR
5) SOLVE FOR DEGRADED CONDITIONS - ASSUME U STAYS CONSTANT
3 equations, 3 unknowns
Solving numerically - Tho (Temperature - Hot Side
- Exit)= 135 F
6) SOLVE FOR DEGRADED CONDITIONS ACCOUNTING FOR FLOW EFFECTS
ON U
Solving numerically - Tho = 141 F
III. Questions Regarding Ethics and Professionalism
1. Should Alison express her reservations about the JCO and request
a delay of the PNSRC vote? Explain.
2. Brad Louks states that the heat exchanger system in question
is "an accident mitigation system, and it's never had to
be used here - or in any other commercial nuclear plant that we
know of, for that matter. In fact lots of plants don't even have
this safety system." Should this ease Alison's concerns
or change her intent to request a vote delay? What part does
Brad's seniority over Alison play?
3. Though not a committee requirement, the PNSRC has always acted
unanimously. In this case, all committee members except Alison
have indicated that they will vote to approve the JCO. How might
this affect Alison's decision?
4. Construct a case where Alison clearly should request a delay
and further investigation (case 1) and a case where she clearly
should not (case 2). Is the actual case closer to case 1 or case
2? Point out similarities and differences between the actual
case and case 1 and case 2 in order o justify your position.
IV. Solutions to Ethical Questions